Procurement procedures for HPPs contracts in Montenegro, Dr Lorenc Gordani, 19th June 2017 Montenegro has rather high natural hydropower potential and accordingly a significant number of hydropower generation projects in the pipeline. The state has quite limited potential to develop projects on its own. The generation incumbent EPCG also does not have any plans to develop new large HPPs. There are potentially two procedures for developing electricity generation objects in Montenegro. The Law on Energy provides for the authorisation procedure and a public tendering procedure. The authorisation procedure is only possible for electricity generation facilities not exceeding 1 MW of installed capacity. On the other hand, Energy Permit is not required in case of developing electricity generation facilities constructed as a result of an organised public tender. Further, since the…